Capital Improvement Projects
Updated - Wednesday, September 14, 2020
- Crack Seal Program 2020
- DPW Truck Wash
- Freshwater Pond Forebay Dredging
- South River Street Bridge Permanent Repair
CRACK SEAL PROGRAM 2020
Contact: J.P. Rodriguez - ROADS Engineer
- The Maintenance Contract awarded to Connecticut Sealcoating LLC
Project Update
The Contractor started the work; the following are the streets for crack seal during the week: Memorial Drive, Laurie Drive, Theresa Street, Bacon Road, Davis Avenue, Field Road, Nonotuck Street, White Street, Alden Avenue and Meeting House Lane.
DPW Truck Wash
Contact: John Cabibbo, P.E - Assistant Town Engineer
Street: Moody Road
Designer: BL Companies
Inspector: TBD
Contractor: TBD
Project Update
The Town worked with BL Companies on design and permitting for a truck wash at the DPW Facility at 40 Moody Road. Engineering received Aquifer Protection and Planning site plan approval.
This project was contracted with Enterprise Builders, Inc. from Newington, Connecticut. The Contractor has acquired a certificate of occupancy and the new Truck Wash is up and functioning.
Freshwater Pond Forebay Dredging
Contact: John Cabibbo, P.E - Assistant Town Engineer
Street: North Main Street
Designer: Wright - Pierce
Inspector: TBD
Contractor: TBD
Project Update
To come into compliance with an existing United States Army Corps of Engineers permit for the Freshwater Pond, the Town worked with Wright -Pierce to develop a plan and to acquire the required permits to remove sediment from the Freshwater Pond forebay near the footbridge, which crosses the Freshwater Brook at the pond entrance. Wright-Pierce has put together a construction contract which includes some vegetation maintenance and natural enhancements around the pond, as required under the original United States Army Corps of Engineers permit.
The Freshwater Pond Forebay Dredging Project contract has been signed. The maintenance work is slated to be started this summer and completed this fall.
South River Street Bridge Permanent Repair (Replacement)
South River Street Bridge Temporary Closure 2-11-2020
Project Update as of June 5, 2019:
The Town has received funding for the replacement of South River Street Bridge. The estimated construction cost for this project is approximately $2.4 million. This project is anticipated to be undertaken with 80 percent Federal funds and 20 percent Town funds. The Town is currently working with a design consultant and the State on the design. The State has approved the preliminary design. There are right-of-way impacts associated with the proposed improvements. These impacts consist of various temporary and permanent rights and easements necessary for construction and maintenance of the bridge, as well as a total acquisition necessary for the realignment of South River Street starting at the Main Street intersection.
The Town of Enfield conducted a Public Hearing concerning South River Street Bridge Replacement, State Project No. 48-198 – jointly with Connecticut River Access Path, State Project No. 48-190 - on April 17, 2019 in the Enfield Town Hall, Council Chambers.
DPW and a representative of State DOT presented the preliminary design for South River Street Bridge Replacement, State Project No. 48-198 to Town Council at the May 6, 2019 Town Council Meeting. The State required Town Council endorsement of the preliminary design for the bridge because it entails property acquisition. After the presentation, Town Council endorsed both the South River Street Bridge Replacement design and the Connecticut River Access Project design.
Construction is anticipated to begin in Spring 2021 based on the availability of funding.
South River Street Bridge Project Public Hearing Notice
Enfield Projects Public Hearing Presentation COMBINED DRAFT 3 (PDF)
Contact: John Cabibbo, P.E - Assistant Town Engineer
Street: South River Street
Designer: GM2 Associates
Inspector: TBD
Contractor: TBD